General — Manufacturing Updates

Natural Gate Manufacturing Status Update: June 16th, 2019

Natural Gate Manufacturing Status Update: June 16th, 2019

Hello folks!

I have some dates from the CM and I'm booking flights to oversee production (which has already started).  SMT has already begun and likely completed by the time this is posted.

Calibration and...


Natural Gate Manufacturing Status Update: May 25th, 2019

Natural Gate Manufacturing Status Update: May 25th, 2019

I will be arranging my flight back to the USA in next month or so based on the final schedule from the manufacturer which I should have soon.  NG batch 3 is coming soon!

And since this...


Natural Gate Manufacturing Status Update: April 20th, 2019

Natural Gate Manufacturing Status Update: April 20th, 2019

Hello folks!

We're on the homestretch here!  The NG batch should be hitting the lines soon.  We're anticipating summer (of 2019 haha).  All the 'extra' parts (front panels, etc. assy hardware, boxes, new cables) are rolling in...


Natural Gate Manufacturing Status Update: March 22th, 2019

Natural Gate Manufacturing Status Update: March 22th, 2019

Ok Natural Gate fans!  I am about to build (just waiting for one part) what I call the 'PP' which is a production prototype.  I always build one by hand anytime the design package changes version...


Natural Gate Manufacturing Status Update: March 5th, 2019

Natural Gate Manufacturing Status Update: March 5th, 2019

Howdy!

Parts are rolling in.  The panels have arrived at screen printing this week then they get shipped out to get machined.

Looking good so far!  No major hiccups (knock on wood!)

Thanks,
RE Team